Sequencing in Live Facilities

Audience: project managers, site engineers, ops leads
Goal: deliver works in occupied/operational facilities with zero surprises, zero harm, and minimal downtime.

Why sequencing matters

  • Production and customer operations cannot stop.
  • Safety risks increase with shared routes, plant and people.
  • Dust/noise/odour can contaminate product or void warranties.
  • Unplanned isolations jeopardise business continuity and insurance.

Principles to run by

  1. Safety leads the programme. No permit, no work.
  2. Operations first. Black-out dates and change freezes trump convenience.
  3. Single truth. One look-ahead, one set of drawings, one comms thread.
  4. Protect interfaces. Movement, utilities and information flow.
  5. Evidence everything. RAMS briefed, permits logged, QA photographed.

Five-stage playbook

1) Discovery & constraints capture

  • Map departments, people flows, FLT routes, fire egress, hygiene zones.
  • Log black-out periods, shift patterns, planned outages, deliveries, audits.
  • Confirm noise/dust limits, cleanliness classes, hot-work rules.
  • Agree a Change Control process (who approves, how fast).

2) Zoning & segregation

  • Physical barriers (solid where dust-sensitive), negative/positive pressure as needed.
  • Mark safe walkways, FLT aisles, fire routes; add access control.
  • Dedicated laydown, waste and charging areas.
  • Daily housekeeping standard (photos at start/finish).

3) Isolation & changeover strategy

  • Electrical/mechanical/process isolations planned with LOTO; create a register.
  • Temporary supplies/bypasses where continuity is required.
  • Pre-commissioning and changeover rehearsals (“dry runs”).
  • Agree revert plan if changeover fails (timeboxed go/no-go).

4) Works windows & micro-sequencing

  • Use nights/weekends or micro-windows between batches.
  • Break tasks into short, testable increments with recovery time.
  • Example (packaging line upgrade):
    1. Pre-build skid off-line → FAT complete
    2. Isolation & disconnect (02:00–03:00)
    3. Remove old conveyor (03:00–04:00)
    4. Lift/position new module (04:00–05:00)
    5. Services hook-up (05:00–06:00)
    6. Cold commission & safety checks (06:00–07:00)
    7. Trial run with product (07:00–07:30)
    8. Contingency/revert window (07:30–08:00)

5) Interfaces, logistics & permits

  • Booked delivery slots and defined routes; spotters for shared areas.
  • Lift plans, TM plans, waste routes; no ad-hoc movements.
  • Permit board: hot works, roof access, MEWP, excavation, confined space.
  • Daily permit review at start-up meeting.

Quality & HSE built into the sequence

  • ITP with hold points tied to windows: isolation proved, fixings torqued, guards fit, interlocks tested.
  • Pre-use checks for access/plant; LOLER/PUWER docs on file.
  • Hygiene sign-off and cleaning records before handback.

Communication cadence (keep it light, keep it regular)

  • Weekly: coordination meeting with operations (review next 2–6 weeks).
  • Daily: 10-minute start-up at the workface (permits, people, plant, plan).
  • Change notices: simple one-pager—what/when/where, risks, mitigations, contacts.
  • Single point of contact on both sides.

Two-Week Look-Ahead (snapshot):

  • Windows confirmed ✔
  • Permits pre-approved (draft) ✔
  • Drawings/IFC issue ✔
  • Plant & access booked ✔
  • Risk hot-spots + contingencies listed ✔

KPIs that actually help

  • Window hit rate % (planned vs achieved)
  • Unplanned disruption count (target: zero)
  • Permit compliance % (briefed, signed, closed)
  • Defects at handback (target: zero blockers)
  • Near-miss reporting (quality over quantity)

Red flags—stop and escalate

  • Permit missing or controls not in place.
  • Overrun threatens start of operations.
  • Unapproved route/plant change.
  • Unexpected utility/service behaviour.
  • Dust/noise/odour exceeding limits or any contamination.
    Action: make safe → notify ops lead → follow revert plan.

Pocket checklist (A5)

  • Latest drawings & single schedule
  • Black-out dates logged
  • Zones & routes marked, barriers erected
  • RAMS briefed; permits ready
  • LOTO kit & isolation plan
  • Delivery slots booked; laydown clear
  • ITP hold points known to crew
  • Housekeeping standard agreed
  • Handback criteria & sign-off names

Photos that prove control

  • Barriers & signage in place
  • Isolation tags & readings
  • Fixings with torque witness marks
  • Guarding/interlocks tests
  • Cleanliness checks at handback
  • Permit board at start/end of shift

Final word

In live facilities, sequencing is risk control. Break the work into safe, testable chunks; protect interfaces; keep comms boringly predictable. Do that and you’ll finish on time with operations still smiling.

Want editable look-ahead, permit board, and handback templates? Email [email protected] and we’ll send a pack aligned to your scope.

Leave A Reply

Your email address will not be published. Required fields are marked *

Speak to a Project Specialist

Share drawings, constraints and target dates; we’ll return a clear programme and risk controls.

Request a Quote